QAS-ELEMENT-COST-POSTCALC
pragmaticBIM.ch/qas-element-cost-postcalc
After award and after the final account, check the unit rates of the cost calculation against award and actual costs per component type and keep the checked benchmarks for future projects.
Starting point
- Specifications and contractor accounts combine work from different components, so component-specific benchmarks cannot be read from them directly.
- Without a documented mapping to product class, component type, and reference quantity, variances between cost calculation, bid, and construction remain unexplained.
Goal & benefit
- Allocate bid, award, and actual costs traceably to component types and reference quantities.
- Show and explain, per component type, the variances between the unit rates of the cost calculation and the costs actually bid and constructed.
- Store only checked unit rates in the cost database and reuse them for early and detailed cost calculations.
Process
- After each award, provide approved mappings between specification items, procurement packages, product classes, component types, and reference quantities with the bid and award costs, and add the actual costs after the final account.
- Allocate costs to component types using the documented quantity and scope shares, check them against the unit rates of the cost calculation, and resolve variances.
- Approve checked unit rates with price basis, included scope, and provenance, then transfer them into the cost database by product class and type.
Deliverable
- Post-calculation with traceable allocation of specification and actual costs to component types and explained variances from the cost calculation
- Updated cost database with approved unit rates and documented included scope
Ways to do it
-
BauPlus Heiniger & Partner AG editorial listing
Construction administration and AVA software for costs to BKP/eBKP, NPK tendering, award and measurement.
Visit vendor · last checked
-
CostX RIB Software editorial listing
Quantity take-off and cost estimating from 2D drawings and BIM models.
Visit vendor · last checked
-
iTWO 4.0 RIB Software editorial listing
Model-based cost planning, tendering and project control (5D).
Visit vendor · last checked
-
Messerli AVA Messerli Informatik editorial listing
AVA software for tendering, contract award and billing based on NPK.
Visit vendor · last checked
-
PROVIS Axept Business Software AG editorial listing
Swiss construction management and tendering software with IFC import, BIM viewer, eBKP/BKP costing and NPK tendering.
Visit vendor · last checked
-
werk-material.online CRB editorial listing
Record and evaluate own projects; map BKP costs to eBKP-H.
Visit vendor · last checked
Suggest a tool All tools and services
Elements involved
Architecture (26)
+18 more
More use cases for Costs & quantities
-
QAS-COST-INTERFACE
Visualize cost interfaces between base building and tenant fit-out
Before tendering and after every contract change, check that the cost bearers in the model match the split between base building and tenant fit-out agreed in the lease.
-
QAS-AWARD-INTERFACE
Visualize award interfaces
Before each tender is sent out, check that every component is assigned to exactly one procurement package of the agreed breakdown - forgotten parts and overlaps at contractor interfaces become visible.
-
QAS-COST-PLAUS
Component cost plausibility check
Check the designer's unit prices against schema.pragmaticbim.ch and the cost database - by product class and type.