Exterior walls provide the basis for area and quantity take-off, building physics, and facade coordination.
Description
- Load-bearing or non-load-bearing exterior wall with full facade build-up.
- Used for quantity take-off, building physics, and envelope coordination.
Modelling guidelines
- In early phases and for simple facades, model as a multi-layer component with full build-up.
- Model storey by storey; split at component and storey boundaries.
- When complexity increases or tool limits apply, model the facade build-up as a separate layer.
- Use and export the appropriate material from the authoring system.
IFC entity
- IFC4
- IfcWall
- IFC4.3
- IfcWall
- IFC2x3
- IfcWall
- Applicability rule
- (entity_ifc4=IfcWall AND IsExternal=TRUE) OR (entity_ifc2x3=IfcWall AND IsExternal=TRUE)
Attributes
| Attribute | Definition | Used in |
|---|---|---|
| PredefinedType |
Kind of exterior wall. Allowed values
|
|
| Reference Pset_WallCommon |
Facade build-up according to the component catalogue (multi-layer component). |
+1 more |
| IsExternal Pset_WallCommon |
Marks an exterior wall. Allowed values
|
|
| Status Pset_WallCommon |
Component status for coordinating work in existing buildings. Allowed values
|
|
| FireRating Pset_WallCommon |
Fire resistance class of the exterior wall according to the fire protection concept. Allowed values
|
|
| AcousticRating Pset_WallCommon |
Weighted sound reduction index Rw [dB] as laboratory/catalogue value - not R'w. |
|
| ThermalTransmittance Pset_WallCommon · W/(m²·K) |
Thermal transmittance U [W/(m²·K)] as laboratory/catalogue value of the component. |
|
| ElementStatus ePset_ElementStatus |
Component status for coordinating work in existing buildings. Allowed values
Note
|
|
| CostInterface ePset_Cost |
Cost interface: base building or tenant fit-out. Allowed values
|
|
| FundingApplication ePset_Cost |
Number of the funding application, so quantities and costs can be filtered by application. Separate several numbers with commas, e.g. |
|
| AwardInterface ePset_Cost |
Procurement package of the component, so interfaces between contractor packages become visible. Allowed values
|
+1 more |
| PlanningInterface ePset_Cost |
Planning interface of the component as a three-digit BKP code, so responsibilities between design disciplines become visible. Allowed values
|
|
| BelowTerrain ePset_Cost |
Marks whether the component sits below ground level. Allowed values
|
+2 more |
| eBKP ePset_Cost |
eBKP-H classification according to SN 506 511 - derivable from IsExternal, LoadBearing, and BelowTerrain. Allowed values
|
|
| CalculatedType ePset_Cost |
Calculated type name for cost and quantity grouping. Logic |
|
| ProductClass ePset_Cost |
Product class as the shared key for costs, tendering, and life-cycle assessment. It is derived where material and component properties determine it unambiguously, otherwise set. In early phases, a reasoned assumption is acceptable. Allowed values
|
|
| UnitPrice ePset_Cost · CHF/m² |
Project- or office-specific unit price per unit of the reference quantity, used to check component costs for plausibility. |
|
| ReferenceQuantity ePset_Cost |
|
|
| Connection ePset_Circularity |
Connection type for detachability (Madaster). Allowed values
|
|
| Accessibility ePset_Circularity |
Accessibility of the connection without destroying the component or surroundings (Madaster). Allowed values
|
|
| Reuse ePset_Circularity |
Share of already reused or recycled material in the component (0.01 - 1.00, e.g. 0.80 = 80 %). |
|
| MaterialOrProductId ePset_Circularity |
Unique ID of the material or product in the linked database (e.g. Madaster, baubook). |
|
| WasteCodes ePset_Circularity |
Waste codes for deconstruction and disposal. Code to VeVA (CH) or EWC/AVV (EU); format as used by Madaster, e.g. |
|
| GlobalTradeItemNumber Pset_ManufacturerTypeInformation |
GTIN (Global Trade Item Number) of the product type; 8, 12, 13, or 14 digits depending on the GS1 structure. |
+1 more |
| HazardType ePset_HazardousMaterial |
Type of hazardous material found by survey on the affected existing component. Allowed values
|
|
| RemovalCategory ePset_HazardousMaterial |
Remediation urgency and action required, as determined by the survey. Allowed values
|
|
| SerialNumber Pset_ManufacturerOccurrence |
Serial number the manufacturer assigns to an individual product; with the GTIN it identifies the product passport for that specific item. |
|
| NetSideArea Qto_WallBaseQuantities · m² |
Net side area of the modelled exterior wall. |
|
| Width Qto_WallBaseQuantities · m |
Thickness of the modelled exterior wall. |
|
| FireRatingRequired ePset_WallRequirement |
Required fire resistance of the component under the fire protection concept. Target value compared with FireRating. |
+1 more |
| ThermalTransmittanceMax ePset_WallRequirement · W/(m²·K) |
Maximum permitted thermal transmittance U [W/(m²·K)] of the component under the energy standard and the building physics concept. Target value compared with ThermalTransmittance. |
+1 more |
| GlobalWarmingPotentialMax ePset_WallRequirement · kg CO₂-eq/m² |
Maximum permitted greenhouse gas emissions from construction [kg CO₂-eq/m²] per square metre of component area under the greenhouse gas target. Target value compared with GlobalWarmingPotential. |
+1 more |
| GlobalWarmingPotential ePset_Wall · kg CO₂-eq/m² |
Greenhouse gas emissions from construction [kg CO₂-eq/m²] per square metre of component area, calculated from the build-up and KBOB life-cycle data. |
|
| AirborneSoundInsulationMin ePset_WallRequirement · dB |
Required airborne sound insulation De [dB] against exterior noise under SIA 181, depending on the exterior noise and the noise sensitivity of the rooms behind. Target value compared with AirborneSoundInsulation. |
+1 more |
| AirborneSoundInsulation ePset_Wall · dB |
Verified airborne sound insulation De [dB] of the installed component under the acoustic verification. |
+1 more |
| ReactionToFire ePset_ReactionToFire |
Reaction-to-fire group (RF) of the component or its surface layer under the VKF fire protection regulations. Basis for checking VKF 14-15 on claddings, coverings and ceilings. Allowed values
Note
|
|
| ReactionToFireRequired ePset_WallRequirement |
Required reaction-to-fire group (the worst group still permitted) of the component under VKF 14-15. Target value compared with ReactionToFire. Allowed values
Note
|
Related elements
-
ARC-SLAB-BALCONY
Balcony
Makes exterior space, the structural concept, and the building envelope jointly verifiable early on and supports reliable permitting and cost decisions.
-
ARC-SLAB-BASE
Base slab
Makes the building support and load transfer into the ground spatially verifiable early and provides design certainty for basements, waterproofing, and excavation.
-
ARC-SLAB-FLOOR
Floor slab
Defines the load-bearing separation between storeys early and provides design certainty for room heights, structure, and building services.