Schedule & coordination
PG-05
pragmaticBIM.ch/pg-05
The aim is not a particular date but a schedule that holds. Schedule certainty comes from coordinating in good time.
Explanation
That means spatial coordination between architecture, structural engineering, and building services, binding openings and coordination zones, and later construction-level verification.
Levels
SCH-01Low
Adopt structural design in the architecture model and keep the coordinated dimensions of the coarse structural components while no detailed structural model exists yet.
SCH-02Medium
Spatial coordination of architecture and MEP, binding adoption of MEP openings and builder-executed masonry in the structural model, planning of coordination zones and MEP schematics, plus early procurement of the elevator installation and timber contractor.
SCH-03High
Deeper coordination and construction preparation: early multidisciplinary coordination, embed - reinforcement and formwork coordination, MEP detail, installation paths, maintenance spaces, complex assembly, site logistics, and model-supported construction and fabrication processes.
Contributing use cases
BES · Ordering
-
BES-ELEVATOR-EARLYTender the elevator installation early
The client tenders the elevator installation early, once the building permit has been granted, and so obtains binding shaft and installation parameters before floor plans, structure, and foundations are developed further, avoiding late redesign.
-
BES-TIMBER-CONTRACTORProcure the timber contractor early
The client procures a timber contractor after the study or preliminary design and involves it in the design, so that the construction is designed only once and to suit the contractor's production and assembly system.
-
BES-PLAN-BOXProcure plan and model stations
Make current drawings, models, and project data directly usable on every active storey, at the place of work.
-
BES-SITE-WLANProcure temporary site Wi-Fi
Procure temporary Wi-Fi amplifiers so that tablets reach the project platform in every work area, including basements without mobile reception.
DES · Design
-
DES-STRUCT-MASONRYAdopt main-contractor masonry in the structural model
Coordinate non-load-bearing interior masonry walls executed by the main contractor with structural engineering and adopt them as binding objects in the structural model.
-
DES-MEP-SCHEMDevelop MEP schematics
Develop MEP system and riser schematics and formally approve them before construction.
-
DES-EMBED-REINFCoordinate embeds and architectural components with reinforcement
Coordinate embeds and cast-in architectural components with reinforcement before concrete placement and maintain them as binding objects in the formwork and reinforcement model.
-
DES-FIRE-MATRIXDevelop the fire cause-and-effect matrix
Formally approve the fire cause-and-effect matrix for detectors, dampers, actuators, and suppression equipment before construction.
-
DES-FLOORINGPlan floor build-ups
Model floor build-ups as areas so finish, subfloor, joints, and quantities can be evaluated reliably for execution.
-
DES-COMPLEX-ASSEMBLYPlan complex assemblies and intermediate states
Visualize and assess assembly options and temporary construction states with simplified models before they cause conflicts on site.
QAS · Quality assurance
-
QAS-ARCH-STRUCT-ADOPTAdopt structural design in the architecture model
Adopt the coordinated dimensions of the coarse structural components in the architecture model while no detailed structural model exists yet.
-
DES-ARCH-MEP-COORDCoordinate architecture and building services
Coordinate MEP routes, equipment, and space requirements with architecture and update both discipline models consistently.
-
DES-STRUCT-MEP-OPENINGSAdopt MEP openings in the structural model
Coordinate MEP opening requirements with structural engineering and, once approved, adopt them as binding openings in the structural model.
-
QAS-COORD-ZONEPlan coordination zones
Define coordination zones in the model and assign them to meetings so that not every model has to be checked against every other model.
-
QAS-EARLY-COORDCoordinate architecture and building services early
Align concept and feasibility early in the model - comparable to a sketch design, without execution detail.
-
QAS-ARCH-STRUCT-COORDCoordinate architecture and structure
Coordinate load-bearing components between the architecture and structural models so that geometric deviations are detected before construction and do not have to be maintained twice.
-
QAS-MEP-DETAILArchitecture - building services coordination in late design stages
Coordinate building services in construction-ready detail from the building-design phase onward so that clashes, connections, and spatial conditions can be checked before construction.
-
QAS-INSTALL-PATHVerify installation access paths
Carry the installation access paths to be kept clear in the model and prove that equipment can be brought in - before large plant or components force alterations and deconstruction.
-
QAS-MAINT-SPACEVerify maintenance spaces
Maintain clear maintenance spaces in the model and prove them clash-free - before plant becomes unmaintainable.
-
QAS-SITE-LOGISTICSCheck site logistics across the construction phases
Plan site logistics volumetrically and keep them current across phases - before ramps, slopes, and space needs surprise on site.
CON · Construction
-
CON-ROOM-LABELManage fit-out room by room with a checklist
Keep the fit-out steps for each room in a shared checklist so that trades work to a takt and the status of every room is visible on site.
-
CON-SHL-BWPCreate formwork and reinforcement plans
Derive formwork and reinforcement plans for concrete execution from the structural model.
-
CON-REINF-EXECReinforcement execution from model
Prepare reinforcement and edge strips from the formwork and reinforcement model for construction execution.
-
CON-FASTEN-SUSPFastening and suspension from model
Plan fastenings and suspensions on the basis of the coordinated structural and MEP models so that they do not have to be improvised on site.
-
CON-PRECAST-ORDERPrecast concrete parts ordering from model
Provide precast concrete parts from the structural model for ordering and delivery planning.
-
CON-ROBOT-LAYOUTSet out the fit-out robotically on the structural slab
Derive the layout file for robotic slab marking directly from the architecture model and print it on the structural slab - so fit-out can start without manual layout errors.
More project goals
-
PG-07
Decision certainty
The aim is to make strategic and design decisions early, comparably, and traceably. Structured use and massing foundations, option comparisons, visualizations, and documented approvals show the consequences of a decision while the project can still be changed.
-
PG-09
Permit certainty
The aim is that the building permit application and official evidence pass without surprises. Requirements for parcels, traffic, parking, accessibility, fire protection, and existing trees are made visible in the model early and checked continuously, as is the evidence for funding.
-