Use case Ordering Schedule & coordination

Tender the elevator installation early

BES-ELEVATOR-EARLY pragmaticBIM.ch/bes-elevator-early

The client tenders the elevator installation early, once the building permit has been granted, and so obtains binding shaft and installation parameters before floor plans, structure, and foundations are developed further, avoiding late redesign.

Starting point

  • Elevator installations are often tendered too late. Different shaft, pit, and headroom dimensions then cause errors and redesign of floor plans, the structure, and foundations.

Goal & benefit

  • Obtain installation-specific dimensions and design parameters in good time and avoid late redesign of the shaft, adjacent spaces, and foundations.
  • Limit the risk of an early award through a right of withdrawal and remuneration for design work in case the project does not go ahead.

Process

  1. Tender and award the elevator installation once the building permit has been granted, including a contractual clause covering the right of withdrawal and remuneration for design work.
  2. Request shaft, pit, headroom, opening, load, and other design parameters from the elevator contractor and have the architecture and structural design teams check them against the design.
  3. Approve the agreed parameters and require their incorporation into the architecture and structural models.

Deliverable

  • Coordinated architecture and structural models with correct shaft geometry and the design parameters of the intended elevator installation incorporated.