Rule Fire protection directive 24-15 Heating plant

Boiler room with direct access from outdoors: above 1,200 kW on ground floor or lower, above 600 kW from 2nd basement

VKF-24-15-005 pragmaticBIM.ch/vkf-24-15-005

Boiler rooms on the ground floor or lower for plants above 1,200 kW nominal heat output, and boiler rooms on the second basement or lower for plants above 600 kW, get direct access from outdoors.

Description

Not yet checkable: the model does not show nominal heat output, fuel, type of installation and fire resistance of the boiler room.

Source

VKF-Brandschutzrichtlinie 24-15 Wärmetechnische Anlagen (2015) (p. 6)

More rules for Fire protection directive 24-15 Heating plant