Rule Fire protection directive 15-15 Fire safety distances, load-bearing structures, fire compartments
Installation shafts over several storeys: compartment-forming, at least EI 30
VKF-15-15-014
pragmaticBIM.ch/vkf-15-15-014
Building-services lines running over several storeys are in principle routed in installation shafts that themselves form fire compartments. The shaft enclosure matches the fire resistance of the use-related compartmentation, but at least EI 30.
Description
A shaft can be omitted where lines pass storey by storey through floors with penetrations made as in clause 3.5 or run in VKF-recognized wall systems. Not yet checkable: the model does not show which components enclose a shaft.
Source
VKF-Brandschutzrichtlinie 15-15 Brandschutzabstände, Tragwerke, Brandabschnitte (2015) (p. 9)
More rules for Fire protection directive 15-15 Fire safety distances, load-bearing structures, fire compartments
-
VKF-15-15-015
Inspection openings of installation shafts: EI 30 closure
Inspection openings in installation shafts are closed with fire-rated closures EI 30. In low and medium-height buildings RF1 inspection covers are sufficient where the shaft is subdivided or filled storey by storey.
-
VKF-15-15-016
Installation shafts: horizontal subdivision at every storey
In installation shafts that are closed at the top, the recesses for lines are closed with RF1 materials at every storey.
-
VKF-15-15-017
Installation shafts: separate flue systems and ducts with enhanced requirements
Flue systems, ventilation ducts with enhanced fire protection requirements and similar lines are separated from each other and from the other installations in the same shaft with 30 minutes of fire resistance made of RF1 materials, e.g. fire protection boards.