Rule Fire protection directive 15-15 Fire safety distances, load-bearing structures, fire compartments
Inspection openings of installation shafts: EI 30 closure
VKF-15-15-015
pragmaticBIM.ch/vkf-15-15-015
Inspection openings in installation shafts are closed with fire-rated closures EI 30. In low and medium-height buildings RF1 inspection covers are sufficient where the shaft is subdivided or filled storey by storey.
Description
Not yet checkable: inspection openings are not modelled as separate elements on shafts.
Source
VKF-Brandschutzrichtlinie 15-15 Brandschutzabstände, Tragwerke, Brandabschnitte (2015) (p. 10)
More rules for Fire protection directive 15-15 Fire safety distances, load-bearing structures, fire compartments
-
VKF-15-15-016
Installation shafts: horizontal subdivision at every storey
In installation shafts that are closed at the top, the recesses for lines are closed with RF1 materials at every storey.
-
VKF-15-15-017
Installation shafts: separate flue systems and ducts with enhanced requirements
Flue systems, ventilation ducts with enhanced fire protection requirements and similar lines are separated from each other and from the other installations in the same shaft with 30 minutes of fire resistance made of RF1 materials, e.g. fire protection boards.
-
VKF-15-15-018
Housing: dwellings as separate fire compartments
Dwellings are built as separate fire compartments. For single-family houses including their basements and an associated granny flat, no fire resistance is required of structure, walls and floors.