Rule Fire protection directive 15-15 Fire safety distances, load-bearing structures, fire compartments

Installation shafts: horizontal subdivision at every storey

VKF-15-15-016 pragmaticBIM.ch/vkf-15-15-016

In installation shafts that are closed at the top, the recesses for lines are closed with RF1 materials at every storey.

Description

The subdivision can be omitted if there is a smoke and heat vent of 5 % of the shaft cross-section at the top leading to the open air that is permanently open or can be opened from a safe place, if the shaft is filled without voids with RF1 materials (in low and medium-height buildings without special installations non-melting RF2 materials suffice), or if only lines made of RF1 materials are present. Not yet checkable: shaft closures, fillings and line materials are not represented in the model.

Source

VKF-Brandschutzrichtlinie 15-15 Brandschutzabstände, Tragwerke, Brandabschnitte (2015) (p. 10)

More rules for Fire protection directive 15-15 Fire safety distances, load-bearing structures, fire compartments

Contact

abstract ag

Imprint · Picassoplatz 4, 4052 Basel