Rule Fire protection directive 15-15 Fire safety distances, load-bearing structures, fire compartments
Combustible pipe insulation interrupted at the penetration
VKF-15-15-013
pragmaticBIM.ch/vkf-15-15-013
Combustible thermal insulation on services is interrupted with RF1 material where the service passes through a wall or floor that forms a fire compartment. For tested and recognized components the VKF recognition applies.
Description
Not yet checkable: pipe insulation and its material are not represented in the model.
Source
VKF-Brandschutzrichtlinie 15-15 Brandschutzabstände, Tragwerke, Brandabschnitte (2015) (p. 9)
More rules for Fire protection directive 15-15 Fire safety distances, load-bearing structures, fire compartments
-
VKF-15-15-014
Installation shafts over several storeys: compartment-forming, at least EI 30
Building-services lines running over several storeys are in principle routed in installation shafts that themselves form fire compartments. The shaft enclosure matches the fire resistance of the use-related compartmentation, but at least EI 30.
-
VKF-15-15-015
Inspection openings of installation shafts: EI 30 closure
Inspection openings in installation shafts are closed with fire-rated closures EI 30. In low and medium-height buildings RF1 inspection covers are sufficient where the shaft is subdivided or filled storey by storey.
-
VKF-15-15-016
Installation shafts: horizontal subdivision at every storey
In installation shafts that are closed at the top, the recesses for lines are closed with RF1 materials at every storey.