Pipe (schematic)
MEP-SCH-PIPE
pragmaticBIM.ch/mep-sch-pipe
Reserves main pipework routes in the initial phase and reduces later clashes.
Description
- Simplified segment or volume for main routes (heating, cooling, water, wastewater, etc.).
- Used for feasibility and clash checking, not for execution planning.
Modelling guidelines
- Model as a volume or simplified segment; cross-section according to the sketch concept.
- Set the medium in Reference (e.g. HZ, KZ, TW, AW, ENT).
- Use only in preliminary design. From the construction project onward, the downpipe is a separate element with Reference
FL. - Do not model fittings, control valves, or connection details.
IFC entity
- IFC4
- IfcPipeSegment
- IFC4.3
- IfcPipeSegment
- IFC2x3
- IfcFlowSegment
- Applicability rule
- (entity_ifc4=IfcPipeSegment AND (Reference=HZ OR Reference=VL-H OR Reference=RL-H OR Reference=KZ OR Reference=VL-K OR Reference=RL-K OR Reference=TW OR Reference=FW OR Reference=AW OR Reference=WW OR Reference=ENT)) OR (entity_ifc2x3=IfcFlowSegment AND (Reference=HZ OR Reference=VL-H OR Reference=RL-H OR Reference=KZ OR Reference=VL-K OR Reference=RL-K OR Reference=TW OR Reference=FW OR Reference=AW OR Reference=WW OR Reference=ENT))
Attributes
| Attribute | Definition | Used in |
|---|---|---|
| Reference Pset_PipeSegmentTypeCommon |
Medium of the schematic pipe. Allowed values
|
+1 more |
| Status Pset_PipeSegmentTypeCommon |
Component status for coordinating work in existing buildings. Allowed values
|
|
| ElementStatus ePset_ElementStatus |
Component status for coordinating work in existing buildings. Allowed values
Note
|
|
| FundingApplication ePset_Cost |
Number of the funding application, so quantities and costs can be filtered by application. Separate several numbers with commas, e.g. |
|
| GrossCrossSectionArea Qto_PipeSegmentBaseQuantities · m² |
Cross-sectional area of the modelled schematic pipe. |
Related elements
-
MEP-SCH-DUCT
Duct (schematic)
Reserves main ventilation routes in the initial phase and reduces later clashes.
-
MEP-SCH-TRAY
Cable tray (schematic)
Reserves main electrical routes in the initial phase and reduces later clashes.
-
MEP-SCH-EQUIP
Plant space (schematic)
Reserves sufficient plant-room space in the initial phase and prevents conflicts with other uses.