Cable tray (schematic)
MEP-SCH-TRAY
pragmaticBIM.ch/mep-sch-tray
Reserves main electrical routes in the initial phase and reduces later clashes.
Description
- Simplified segment or volume for main trays and risers.
- Used for feasibility and clash checking, not for execution planning.
Modelling guidelines
- Model as a volume or simplified segment; cross-section according to the sketch concept.
- Set the medium in Reference (e.g. EL).
- Do not model cables, detailed fittings, or secondary conduits.
IFC entity
- IFC4
- IfcCableCarrierSegment
- IFC4.3
- IfcCableCarrierSegment
- IFC2x3
- IfcFlowSegment
- Applicability rule
- entity_ifc4=IfcCableCarrierSegment OR entity_ifc2x3=IfcFlowSegment
Attributes
| Attribute | Definition | Used in |
|---|---|---|
| Reference Pset_CableCarrierSegmentTypeCommon |
Medium of the schematic cable tray. Allowed values
|
|
| Status Pset_CableCarrierSegmentTypeCommon |
Component status for coordinating work in existing buildings. Allowed values
|
|
| ElementStatus ePset_ElementStatus |
Component status for coordinating work in existing buildings. Allowed values
Note
|
|
| CostInterface ePset_Cost |
Cost interface: base building or tenant fit-out. Allowed values
|
|
| FundingApplication ePset_Cost |
Number of the funding application, so quantities and costs can be filtered by application. Separate several numbers with commas, e.g. |
|
| AwardInterface ePset_Cost |
Procurement package of the component, so interfaces between contractor packages become visible. Allowed values
|
|
| PlanningInterface ePset_Cost |
Planning interface of the component as a three-digit BKP code, so responsibilities between design disciplines become visible. Allowed values
|
|
| BelowTerrain ePset_Cost |
Marks whether the component sits below ground level. Allowed values
|
|
| eBKP ePset_Cost |
eBKP-H classification according to SN 506 511 - derivable from element type, medium, and BelowTerrain. Allowed values
|
Related elements
-
MEP-SCH-EQUIP
Plant space (schematic)
Reserves sufficient plant-room space in the initial phase and prevents conflicts with other uses.
-
MEP-DOWNPIPE
Downpipe
Secures roof and balcony drainage by coordinating routes, connections, and slab penetrations.
-
MEP-CHILLER
Chiller
Secures cooling supply by coordinating capacity, plant footprint, and service connections early.