Use case Construction Costs & quantities

Determine final quantities for contractor accounts from the model

CON-FINAL-MEASUREMENT pragmaticBIM.ch/con-final-measurement

Derive final quantities from the updated construction model so that contractors' final accounts can be checked and approved faster.

Starting point

  • Contractors and site management often determine final quantities separately; discrepancies only become visible in the final account and are costly to verify.
  • Geometric actual quantities from the model may differ from NPK measurement provisions, whose simplifications are intended for manual measurement. Without an explicit agreement in the tender and works contract, there is no sufficiently defined basis for payment.

Goal & benefit

  • Establish a shared, traceable quantity basis for contractors, site management, and cost planning.
  • Check and approve final accounts faster, improve contractors' cash flow, and encourage market adoption of model-based payment processes.

Process

  1. Define actual measurement, deviations from NPK measurement provisions, model scope, responsibilities, tolerances, cut-off date, and the treatment of unmodelled work and change orders clearly in the tender and works contract.
  2. Update the construction model to the work actually executed, then check completeness and changes against site records and approved change orders.
  3. Derive account quantities by item from the frozen model state, reconcile them jointly, document discrepancies, and approve them as the basis for the final account.

Deliverable

  • Measurement and payment rules agreed in the tender and works contract, explicitly identifying deviations from NPK measurement provisions.
  • Frozen, auditable model state of the executed work with final quantities by item.
  • Reconciliation and approval record for the final account with documented discrepancies.

Ways to do it

  • BauPlus Heiniger & Partner AG editorial listing

    Construction administration and AVA software for costs to BKP/eBKP, NPK tendering, award and measurement.

    Visit vendor · last checked

  • CostX RIB Software editorial listing

    Quantity take-off and cost estimating from 2D drawings and BIM models.

    Visit vendor · last checked

  • iTWO 4.0 RIB Software editorial listing

    Model-based cost planning, tendering and project control (5D).

    Visit vendor · last checked

  • Messerli AVA Messerli Informatik editorial listing

    AVA software for tendering, contract award and billing based on NPK.

    Visit vendor · last checked

  • Messerli BauAD Messerli Informatik editorial listing

    CAD for building design with quantity take-off for handover to tendering (AVA).

    Visit vendor · last checked

  • PROVIS Axept Business Software AG editorial listing

    Swiss construction management and tendering software with IFC import, BIM viewer, eBKP/BKP costing and NPK tendering.

    Visit vendor · last checked

  • SORBA AVA SORBA editorial listing

    AVA software for tendering, contract award and billing based on NPK.

    Visit vendor · last checked

Suggest a tool All tools and services

Elements involved

More use cases for Costs & quantities

Contact

abstract ag

Imprint · Picassoplatz 4, 4052 Basel