Architecture - MEP coordination in later phases (structural openings)
QAS-ARCH-MEP-OPENINGS · General · Quality assurance
Coordinate architecture and MEP in later phases and carry openings and recesses bindingly in the structural model.
Starting point
- Late MEP routes and equipment placements create openings that are often missing in the structural model or only exist in 2D drawings.
- Missing or late openings in the structural model cause clashes, variations, and construction delay.
Goal & benefit
- Align architecture, MEP, and structural models during detailed design on clashes and penetrations.
- Model MEP requests as provisions for void and document approved openings bindingly in the structure.
- Carry openings in non-load-bearing architectural components and masonry in the architecture model.
Process
- Provide architecture and MEP models with near-execution geometry for coordination.
- Request structural openings and recesses as provisions for void in the MEP model; model openings in architectural hosts in the architecture model.
- Model approved openings in the structural model and check them in the federated model.
Outcome
- Aligned ARCH - MEP coordination with approved openings in the structural model and a clear role split per discipline model.
Deliverables
- Architecture, MEP, and structural models with IfcProject, IfcSite, IfcBuilding, and IfcBuildingStorey
- Provisions for void as IfcBuildingElementProxy in the MEP model (PredefinedType=PROVISIONFORVOID; IFC2x3 ObjectType=PROVISIONFORVOID)
- Approved openings and recesses as IfcOpeningElement in the structural model (PredefinedType OPENING or RECESS)
- Openings in architectural components as IfcOpeningElement in the architecture model (PredefinedType OPENING or RECESS)
- Aligned Name and Reference between MEP provision for void and structural opening
- Location and dimensions of the opening for structural approval
Activated by project goals
- Schedule criticality · medium