Duct (schematic)
MEP-SCH-DUCT
Schematic duct for early coordination - medium in Reference.
Description
- Simplified segment or volume for main duct routes (supply / extract, etc.).
- Used for feasibility and clash checking, not for execution planning.
Modelling guidelines
- Model as a volume or simplified segment; cross-section according to the sketch concept.
- Set the medium in Reference (e.g. ZU, AB).
- Do not model fittings, fire dampers, or connection details.
Attributes
| Name | Description | Unit |
|---|---|---|
|
Reference
Pset_DuctSegmentTypeCommon |
Medium of the schematic duct. Allowed values
|
|
|
GrossCrossSectionArea
Qto_DuctSegmentBaseQuantities |
Cross-sectional area of the modelled schematic duct. |
m² |
|
Status
Pset_DuctSegmentTypeCommon |
Element status for coordination on existing buildings. Allowed values
|
|
|
ElementStatus
ePset_ElementStatus |
Element status for coordination on existing buildings. Allowed values
Note
|
|
|
CostInterface
ePset_Cost |
Cost interface of the component - base building or tenant fit-out. Allowed values
|
|
|
AwardInterface
ePset_Cost |
Award package of the component by three-digit BKP code - so interfaces between contractor packages become visible. Allowed values
|
|
|
PlanningInterface
ePset_Cost |
Planning interface of the component by three-digit BKP code - so responsibilities between planning disciplines become visible. Allowed values
|
|
|
BelowTerrain
ePset_Cost |
Marks whether the component is below terrain. Allowed values
|
|
|
EbkpH
ePset_Cost |
eBKP-H classification according to SN 506 511 - derivable from element type, medium, and BelowTerrain. Allowed values
|